JORDAN HYDROELECTRIC PLANT

INSTALLATION WORK WEEKS OF 8-15/22-11

 

>>HOME<

2 UNITS 4.5 MW

----UNDER CONSTRUCTION----

2- MODULAR KAPLAN TURBINE GENERATOR UNITS

US ARMY CORPS OF ENGINEERS' DAM

---JORDAN DAM INSTALLATION---

Module 1 Lift Carriage Installation

Weeks of 8-15-11 / 8-22-11

* Note

Carriage is being installed partially plated and not galvanized to test the fit and performance. 

After acceptable operation is proven by installing the east side module, the carriage will be removed, completed and galvanized

Lift cylinder rod eye / trunnion mounts

 

Setting headgate section into east bay slot

Lift carriage

 

Headgate section

Weight 58,000 pounds

 

Lift carriage cam operator air cylinders

Lower lift cams

Downstream flume wall

Transport flume wall to tower roof