JORDAN HYDROELECTRIC PLANT INSTALLATION WORK WEEK OF 8-8-11 |
2 UNITS 4.5 MW |
----UNDER CONSTRUCTION----
2- MODULAR KAPLAN TURBINE GENERATOR UNITS
US ARMY CORPS OF ENGINEERS' DAM
---JORDAN DAM INSTALLATION---
Module 1 Lift Carriage Installation
Week of 8-8-11
* Note
Carriage is being installed partially plated and not galvanized to test the fit and performance.
After acceptable operation is proven by installing the east side module, the carriage will be removed, completed and galvanized
Downstream side of carriage |
Downstream slide block and side roller |
Upstream shim blocks west side of east bay |
Upstream shim blocks east side of east bay |
Upstream shim blocks and downstream slot plates |
Downstream water quality slot plates for Carriage |
|
Carriage slide blocks bearing on plates |
|
|
|
Lifting cams |
Carriage in slot supported by E-beam mounted hoist rings and slings
|