JORDAN HYDROELECTRIC PLANT

90-TON CRANE SETUP

 

>>HOME<

2 UNITS 4.5 MW

----UNDER CONSTRUCTION----

2- MODULAR KAPLAN TURBINE GENERATOR UNITS

US ARMY CORPS OF ENGINEERS' DAM

---JORDAN DAM INSTALLATION---

Weeks of 6-20-2011 / 6-27-2011

PLATFORMS

PLATFORMS

STRIPPED 90-TON LINKBELT RTC 8090 SERIES II DRIVEN ACROSS TOWER ROOF WITH 57.5 DEGREE BOOM FOR 50/50 AXLE LOADING

TRANSPORTING DOWNSTREAM OUTRIGGER SUPPORT BEAMS USING 

EQUIPMENT TRAILER AND 10K MLULL

TIGHT TURN AT BRIDGE

 

CRANE JACKED UP ON TIMBERS TO CLEAR SUPPORT BEAM

FULLY RETRACTED OUTRIGGER ON CENTER ROOF BEAM

FULLY EXTENDED OUTRIGGER ON SIDE WALL

CRANE JACKED UP AND WOOD CRIBBING PLACED UNDER TIRES

 

DS SUPPORT BEAMS PLACED DOWNSTREAM OF OUTRIGGERS

PUSHED UNDER OUTRIGGERS BY MLULL FORKLIFT

 

COMPLETED SETUP

OUTRIGGER LOADS TRANSMITTED BY DS SUPPORT BEAMS TO SIDE WALLS

 

BARGE SECTIONS MOVED FROM FRONT OF TOWER TO EAST SIDE

JLG 800A ARTICULATING PERSONNEL LIFT LOWERED ONTO BARGES

 

BARGE WITH LIFT REPOSITIONED ON NORTH END OF TOWER

 

SETTING UPSTREAM SUPPORT COLUMNS

 

 

SETTING UPSTREAM SUPPORT BEAM

 

 

SETTING PLATFORMS

 

 

RAILS

 

 

 

 

LOWER PLATFORM EAST SUPPORT BEAM

 

UPPER PLATFORM VIEW FROM BELOW

 

ANCHORING