JORDAN HYDROELECTRIC PLANT GSU INSTALLATION / TRASHRACKS / LOWER PLATFORM |
2 UNITS 4.5 MW |
----UNDER CONSTRUCTION----
2- MODULAR KAPLAN TURBINE GENERATOR UNITS
US ARMY CORPS OF ENGINEERS' DAM
---JORDAN DAM INSTALLATION---
Week of 4-25-2011 / 5-2-2011
5 MVA TRANSFORMER |
TRANSFORMER CONTAINMENT |
TOWER CONDUIT INSTALLATION
TRANSPORTING E BEAM TO TOWER ROOF |
INSTALLING DOGGING ARMS |
|
E BEAM - 20,000+ POUNDS |
|
CENTER DOGGING ARMS |
E BEAM / LIFT BEAMS
RANDY / BILL / NICK
ASSEMBLY OF TRASHRACK SUPPORT STEEL |
|
EAST SIDE TRASHRACK SUPPORT STEEL |
EAST SIDE TRASHRACK SUPPORT STEEL ANCHORED IN PLACE UNDERWATER |
FRONT TRASHRACK SUPPORT BEAMS |
|
TRASH RACK SUPPORT BEAMS |
CENTER PIER NOSING CHANNEL MODIFICATION |
TRASH RACK PANELS |
LOWER PLATFORM EAST SUPPORT BEAM |
LOWER PLATFORM CENTER SUPPORT BEAM |
|
LOWER PLATFORM SUPPORT STEEL