JORDAN HYDROELECTRIC PLANT

UNDERWATER CONCRETE CUTTING

>>HOME<

2 UNITS 4.5 MW

----UNDER CONSTRUCTION----

2- MODULAR KAPLAN TURBINE GENERATOR UNITS

US ARMY CORPS OF ENGINEERS' DAM

---JORDAN DAM INSTALLATION---

WIRE SAWING AND REMOVAL OF THREE FEET THICK CONCRETE SLABS 20 FEET UNDERWATER

6 SECTIONS / 3' X 4' X 11.5' 22,000 POUNDS EACH

Week of 3-21-2011 / 3-28-2011

DIAMOND WIRE SAW BARGE SETUP

BLUEGRASS COMPANIES

GRAINGER UNDERWATER SERVICES

BARGE SETUP FOR SAWING OPERATIONS

TRANSFORMER CONTAINMENTS STEEL SHIELD WALL

 

RANDY CARNES / BILL CARNES / JASON KARKIEWICZ

GRAINGER UNDERWATER SERVICES / BC WELDING

 

TOWER CONTROL BOOTH CONDUIT ACCESS PLATFORM

35-TON ROUGH TERRAIN CRANE SETUP ON TOWER ROOF

50,000# 2 1/2" SWIVEL HOIST RING FOR SIDE CONCRETE SLABS

 

DIVERS THREADING CUTTING WIRE

EAST SIDE, CENTER SLAB CUTTING. 15 FEET DEEP

PAUL CHIEBOWSKI / 22,000# CENTER CONCRETE BLOCK

4+ FEET WIDE X 3 FEET THICK X 11 FEET LONG - 22,000#

MLULL 10K EXTENDED BOOM FORKLIFT / PINTLE HITCH ATTACHMENT

60,000# OFF ROAD RATED EQUIPMENT TRAILER

2 BLOCKS - 42,000#

4-PART RIGGING FOR CENTER BLOCKS