JORDAN HYDROELECTRIC PLANT

INSTALLATION WORK WEEK OF 10-31 2011

 

>>HOME<

2 UNITS 4.5 MW

----UNDER CONSTRUCTION----

2- MODULAR KAPLAN TURBINE GENERATOR UNITS

US ARMY CORPS OF ENGINEERS' DAM

---JORDAN DAM INSTALLATION---

Module 1 East bay slot installation

Generator double columns

 

 

 

 

 

 

 

WEEK OF 10-24-11

Generator floor slot screwjacks

 

Lowering Module

 

 

 

Generator booth roof removed

 

 

 

1 1/2 feet above sill, Service Gate opened to flush sill

 

 

 

 

     

Lifting Cam engagement

 

 

View of lift carriage from Generator Booth

 

Generator floor / top mid-shaft

 

 

View of complete Module lowered to generating position