JORDAN HYDROELECTRIC PLANT

INSTALLATION WORK WEEKS OF 10-17 / 10-24, 2011

 

>>HOME<

2 UNITS 4.5 MW

----UNDER CONSTRUCTION----

2- MODULAR KAPLAN TURBINE GENERATOR UNITS

US ARMY CORPS OF ENGINEERS' DAM

---JORDAN DAM INSTALLATION---

Module 1 East bay slot installation

Rope access for installing bolts in Flume Section

 

 

 

 

 

 

 

Bearing spiders

Graphite impregnated phenolic 4-block water bearings

 

Welding receptacle

Intake Section

WEEK OF 10-24-11

Booth disassembly / Generator loading in Crumpler

 

 

 

 

 

Upending flume section on tower roof

 

 

 

Grease bearing floor

 

Generator floor / booth transport to tower roof

 

Generator floor / booth installed on Module

 

 

     

Flume Section side view above Turbine Section